In the screen shot below, i have applied 7 days work week for project duration activity, start miletone and finish milestone , for all other its 6 days work week calender. On the overall summary level original duration is '959 days' , even though activity project duration is of duration 1095 days. i want to show original duration for project as 1095 days.[[wysiwyg_imageupload:6603:height=300,width=625]]
Project duration not reflecting overall original duration
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Its a function of how P6 calculates durations for summary bands. If all tasks within a summary band use one calendar, then the summary band will also show duration using that calendar.
If there are a mix of calendars, then the summary band will use the project default calendar. So you may want to swtich 5the project default calendar to the 7 day week calendar you are using for the summary activity.