Using Acumen Fuse DCMA 14. Test 12 Critical Path test returns "N" on single project. But when performed with other projects same project returns "N/A". I can't find anywhere that explains why this is "N/A". Has anyone any idea as to why and what I can do to fix it? Thanks.
Acumen Fuse DCMA 14
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Am am not sure how accumen Fuse works but what I do know is what test #12 tests for
This is a ‘what-if’ test performed directly on the schedule. Identify a critical activity and its current remaining duration. You then modify that activity’s remaining duration to be 600 working days and then re-calculate the schedule dates.
You must identify the final critical activity in the schedule and look to see if that activity was delayed by the approximate number of days that you added to the critical path.
"True Critical Path test", If you inserted a 600 day activity into the critical path and see of the end date shifted by 600 days", if not then it is not a True Critical Path.
My guess is that there is float contained in your schedule.