Duration Difference - At Completion Duration based on Default Calendar

Hello Everyone,

The is a Difference in Duration in the WBS. The Project Duration is shown as 174 Days and Milestone Duration is 243 Days (which is the calendar days).

wbs_date.jpg

 

I have 3 Types of Calendar in the Project a). 5 Days Work Week, b). 6 Day Work Week and c). 7 Day Work Week.

The Default Calendar of the Project is 7 Days Work Week.

Could you please guide me on how to show in the Project Duration as 243 Days (Calendar Days).

 

Regards

Jithin

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

HI Everyone,

 

Got the Answer after doing some research,

 

I went to Enterprise - Calendars - Global Section - Then I moved Default Calandar Tick from the Calendar which had a 5 Day Work week to 7 Day Work Week.

Now the Total Duration is same as the the Below WBS Duration.

 

Regards

Jithin

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts