Resources for labor in project

H
Hussein ali 👤 Member for 9 years 2 months

Hi planners >>>

Can I add resources per day?

For example : I want to add 2 Engineers for every day , not for every activity , only for day and don't want to see how many of activities in this day.

R
Rafael Davila 👤 Member for 22 years 3 months

In case the resources shall be assigned full time to certain activities these must be leveled so the activities will not happen at the same time; the hammock can be resource loaded with variable workload and min workload equal to 0.  In this way when not assigned to any specific activity it will be assigned to the hammock.

The most common HORROR I have seen is to assign a crane to a hammock and not resource level it, there is a limit on how much work a crane can do on a single day!

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Create hammock activity and assign 2 engineers on this hammock that lasts from the start to the finish of your project (subproject). Don't assign these engineers to other activities.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts