I have a question from my university, hope it's ok to ask it here.
So both NPV and DPP are used to determine the profitability of a project. But what are the advantages/pros of each of them and in what kind of project/condition will NPV be valued more than DPP and vice versa?
Thank you for any help you can provide.
NPV and DDP preference?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
DPP and NPV show different data - a moment when the profit will cover expenses and overall discounted profit. One does not replace another.
I suggest to add IRR to these parameters.