Progress Variance Vs Finish Date

F
Fahad Ali 👤 Member for 9 years 7 months

Hi

My percent complete type is duration. I had a baseline that had actual dates and now program mitigated and revised. So my previously updated program is now a baseline for current update. Problem that I am facing here is, my activity progress variance is not matching with Finish date.

 

For example: actual progress is 80% and planned is 90%. remaining baseline duartion was 35 and remaining duration now is 11 which is not matching my actual progress of 80%. As per my actual percentage, remaining duration should be 7(20%*35). It is P6 version 8.2. Please advice.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts