Can anyone guide me in the best direction on how to schedule compensation events into the project baseline? Im working under the NEC contract.
Thanks
James
Hi all
Apologies if this has aready been asked / answered.
Can anyone guide me in the best direction on how to schedule compensation events into the project baseline? Im working under the NEC contract.
Thanks
James
Hi James
It is the same method as described in an Impacted as Planned delay analysis method.
1. Calculate the duration of the compensation event.
2. Set this into a Sub Chart.
3. Link to the affected task(s).
4. Hit F9 and wait for the howls of protest from the CA.
Best regards
Mike Testro