Hi all

 

Apologies if this has aready been asked / answered.

Can anyone guide me in the best direction on how to schedule compensation events into the project baseline? Im working under the NEC contract.

Thanks 

James

M
Mike Testro 👤 Member for 20 years 5 months

Hi James

It is the same method as described in an Impacted as Planned delay analysis method.

1. Calculate the duration of the compensation event.

2. Set this into a Sub Chart.

3. Link to the affected task(s).

4. Hit F9 and wait for the howls of protest from the CA.

Best regards

Mike Testro