Report: Current Week Activities

Hello Guys,

I would like to create a report that displays the to-do list of the acitvities grouped by project of the current week, supposed that I run the report on monday. I cannot manage to create it. How can I make it?

 

Thank you

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

Suggests to assign activity codes to use for grouping and filter using Current Day+7d

 

R
Robert Bell 👤 Member for 9 years 11 months

Hi Stefano,

You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

R
Robert Bell 👤 Member for 9 years 11 months

Hi Stefano,

You can do this by filtering for the dates. The only thing to be wary of is if you filter for work in the fourth week of the month for example, but the activities for the first three did not go as planned and are still open.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Stefano, it depends on the software that you use.

In Spider Project you just select the period and that's all. It is standard function.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts