This will depend on a number of things. The most obvious being whether or not you have changed the logic. Obviously doing this can affect the project by much more than a month in a month. Another thing will be your data date. Perceivably you might schedule this on 31 days. The most surprising reason that could cause the date to slip by greater than one month however, without adding any additional logic or increasing durations is in fact, reducing a duration on an activity with a SS relationship type.
Example - Consider a situation where you have three activities, each with a duration of 50 days. A, B and C. There is logic between each of these in the form of a FF relationship from A to B, and a SS relationship from B to C and prior to scheduling on, these activities are all perfectly aligned. Now imagine that activity A has been delayed by the full month in a month due to additional logic feeding this activity, be that 20, 30, 31 days etc dependant on calendars and data date movements. This change will thus move activities B and C by this same amount of time. Additionally, it is possible that on top of this movement of activity A, activity B will for some reason have a duration reduction from 50 to 20 days as part of the month end update (new information/reforecasting etc). This shortening of activity B will not have an affect on its finish date since that is still anchored by activity A's delayed finish date. It's start date however, will have to move to the right (assuming it does not already have an actual start). This delay to activity B's start will now impact activity C's as well and therefore it's finish date, which had already been delayed by the slippage of activity A. Ultimately, there has only been a month's delay on preceeding activities but other changes have caused activity C to be delayed by 60 days.
This will depend on a number of things. The most obvious being whether or not you have changed the logic. Obviously doing this can affect the project by much more than a month in a month. Another thing will be your data date. Perceivably you might schedule this on 31 days. The most surprising reason that could cause the date to slip by greater than one month however, without adding any additional logic or increasing durations is in fact, reducing a duration on an activity with a SS relationship type.
Example - Consider a situation where you have three activities, each with a duration of 50 days. A, B and C. There is logic between each of these in the form of a FF relationship from A to B, and a SS relationship from B to C and prior to scheduling on, these activities are all perfectly aligned. Now imagine that activity A has been delayed by the full month in a month due to additional logic feeding this activity, be that 20, 30, 31 days etc dependant on calendars and data date movements. This change will thus move activities B and C by this same amount of time. Additionally, it is possible that on top of this movement of activity A, activity B will for some reason have a duration reduction from 50 to 20 days as part of the month end update (new information/reforecasting etc). This shortening of activity B will not have an affect on its finish date since that is still anchored by activity A's delayed finish date. It's start date however, will have to move to the right (assuming it does not already have an actual start). This delay to activity B's start will now impact activity C's as well and therefore it's finish date, which had already been delayed by the slippage of activity A. Ultimately, there has only been a month's delay on preceeding activities but other changes have caused activity C to be delayed by 60 days.
Delays might be a function of calendars. If you delay a critical activity execution by one month and this put it into a winter season then it might become on hold several months after the winter, therefore delaying the completion of job.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Arun,
This will depend on a number of things. The most obvious being whether or not you have changed the logic. Obviously doing this can affect the project by much more than a month in a month. Another thing will be your data date. Perceivably you might schedule this on 31 days. The most surprising reason that could cause the date to slip by greater than one month however, without adding any additional logic or increasing durations is in fact, reducing a duration on an activity with a SS relationship type.
Example - Consider a situation where you have three activities, each with a duration of 50 days. A, B and C. There is logic between each of these in the form of a FF relationship from A to B, and a SS relationship from B to C and prior to scheduling on, these activities are all perfectly aligned. Now imagine that activity A has been delayed by the full month in a month due to additional logic feeding this activity, be that 20, 30, 31 days etc dependant on calendars and data date movements. This change will thus move activities B and C by this same amount of time. Additionally, it is possible that on top of this movement of activity A, activity B will for some reason have a duration reduction from 50 to 20 days as part of the month end update (new information/reforecasting etc). This shortening of activity B will not have an affect on its finish date since that is still anchored by activity A's delayed finish date. It's start date however, will have to move to the right (assuming it does not already have an actual start). This delay to activity B's start will now impact activity C's as well and therefore it's finish date, which had already been delayed by the slippage of activity A. Ultimately, there has only been a month's delay on preceeding activities but other changes have caused activity C to be delayed by 60 days.
It's an uncommon scenario but one to be aware of.
Arun,
This will depend on a number of things. The most obvious being whether or not you have changed the logic. Obviously doing this can affect the project by much more than a month in a month. Another thing will be your data date. Perceivably you might schedule this on 31 days. The most surprising reason that could cause the date to slip by greater than one month however, without adding any additional logic or increasing durations is in fact, reducing a duration on an activity with a SS relationship type.
Example - Consider a situation where you have three activities, each with a duration of 50 days. A, B and C. There is logic between each of these in the form of a FF relationship from A to B, and a SS relationship from B to C and prior to scheduling on, these activities are all perfectly aligned. Now imagine that activity A has been delayed by the full month in a month due to additional logic feeding this activity, be that 20, 30, 31 days etc dependant on calendars and data date movements. This change will thus move activities B and C by this same amount of time. Additionally, it is possible that on top of this movement of activity A, activity B will for some reason have a duration reduction from 50 to 20 days as part of the month end update (new information/reforecasting etc). This shortening of activity B will not have an affect on its finish date since that is still anchored by activity A's delayed finish date. It's start date however, will have to move to the right (assuming it does not already have an actual start). This delay to activity B's start will now impact activity C's as well and therefore it's finish date, which had already been delayed by the slippage of activity A. Ultimately, there has only been a month's delay on preceeding activities but other changes have caused activity C to be delayed by 60 days.
It's an uncommon scenario but one to be aware of.
Delays might be a function of calendars. If you delay a critical activity execution by one month and this put it into a winter season then it might become on hold several months after the winter, therefore delaying the completion of job.