Manpower loading

hi,

guys i have 30activities, which is finish to start.

and i have only 2men to complete all 33 activities.

how can i allocate just 2men.

My total manpower after allocation should show me 2men.

 

Thanks & Regards,

 

Vigeeth

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Assign those who will do the work, enter resource availability (two men) and then level project resources.

The software will organize the sequence of work so that at any time not more than two men will be used. It does not matter if your activity dependencies are FS or others, or no dependencies at all.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Vigeeth

Just allocate 2 men to each of the tasks - when the logic is FS with no lead lags the histogram should show a straight line of 2 men allocated.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts