Hi all,
Does anyone know how can we show a range of selested activities and their relatioships (Predec and Succ) in Gant Chart in P6. I mean just showing selected activities and their relationship in Gant Chart.
I know with codes we can do that but it's not general. I want to show those exactly like network view but in Gant Chart.
Thanks
Thanks Vladimir,
It's in P6. So I will ask in it's forum.
Thanks again
Ehsan,
you did not specify your software. If you use specific tool ask this question in this software forum.
In Spider Project this is easy: select required activities in the Gantt Chart, right click on any of selected activities number, in the pop-up menu select Filter/Activites Linked with Selected Only.
You will see Gantt Chart of the subnetwork, consisting of activities linked with selected.