Progressing a Schedule Before Baselining

Hello,

After building the project schedule, but before reaching an agreed-to baseline with the client, is it ok to enter progress dates into activities that have taken place in the time between putting the schedule together and reaching the agreed-upon baseline with the client? Or is there a different standard method for doing this?

R
Raymund de Laza 👤 Member for 16 years 6 months

The idea is that the baseline shall be scheduled as current status but not statused as actual. Meaning the schedule is planned as current status. Once accepted as baseline then create a copy to update and statuses the activities accordingly.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Jordan

I take the opposite view to Patrick.

The progress data should reflect what actually happened so it should be added to your "trial" programme.

If changes are required to get approval then the new programme is easily progressed a second time.

Best regards

Mike Testro

Profile picture for Patrick Weaver
Patrick Weaver 👤 Member for 25 years 4 months

Not a good idea - the baseline may be adjusted to reflect what is actually happening but generally the 'baseline' is the planned situation. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts