Earned Value Adjustment

A
Amro Ahmed 👤 Member for 17 years 5 months

Hi All,

There is earned value adjustment shall be done in case Of Finishin the activity less than BAC.

let me clarify:

Act  A1000  BAC =1,000,000 U.S.D   ACT ST 01-DEC-15   ACT FS 30-DEC-15       Finished at 500,000 U.S.D

Options:

1- updae 100%  and actual dates  -impact showing EV=1,000,000 INSTEAD OF 500,000

2- Update 50% ,actual start and ETC=0 - Impact Showing the activity in progress ehile in reality it has been finished

3- Update 100% with actual dates and add new activity with -500,000 to B.L then update -Impact BAC will change from 1,000,000 to 500,000  which not correct

Im convenced with option 1 while my superior convenced with option 3 and im trying to convence

Please advice about the propper one and if there is any other option?

 

Thanks

P
Paul Kidston 👤 Member for 23 years 4 months

Option 1 is clearly the "correct" answer, unless budgetting errors are being corrected, in which case the organisations procedurs should state how to proceed.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts