Claim delay submission

M
moh ham 👤 Member for 15 years 3 months

Can anybody advice if there is any code or standard mention the  contain of the claim submission by the contractor, and can I instruct the contractor as an engineer for the project to use a specified way of analyzing the claim such as window analysis for example.

Thank you

M
Mike Testro 👤 Member for 20 years 5 months

Hi Moh

If you are receiving a delay claim for review it is best to wait until the submission arrives and then make comments.

If you try to restrict the claimant's methods it will work against you if it goes to a dispute tribunal.

In any case I would never suggest a Windows analysis.

Best regards

Mike Testro

Z
Zoltan Palffy 👤 Member for 16 years 10 months

I think you need to first look at what your scheduling specifcation says in that regard. If it is silent you can certainly recommend an analysis type and point out the pros and cons of using this type of analysis 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts