CCPM vs.CPM

How many are reading all of the technical articles concerning CCPM (Critical Chain Project Method)? What is everyone's thought on this?

R
Rafael Davila 👤 Member for 22 years 3 months

It is not only about which procedure is better but about CCPM being flawed.

CCPM proposes that Critical Chain shall never change and this is a major flaw!  

V
Vladimir Liberzon 👤 Member for 25 years 4 months

For reliable project management it is necessary to create and to manage contingency reserves (buffers). If your software includes risk management capabilities and calculates required contingency reserves then use Success Driven Project Management (http://spiderproject.com/images/img/pdf/SDPM%20Approach%20to%20project%…).

But if you manage your projects without the software then CCPM is fine. You will create some initial schedule and add buffers to keep it stable. And then instead of rescheduling you will consume buffers. Easy and nice solution.

And of course in any case resource constraints shall be taken into account. So CPM is not the right term because classical Critical Path Method does not consider resource constraints. Good schedule is leveled and Resource Critical Path (or Critical Chain) replaces classical Critical Path.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts