Primavera Risk Analysis

Hi,

 

I'd like to manage portfolio with PRA and I want to define 2 or more different risk scoring for project level & portfolio level.

How can I switch the qualitative assessment between these 2 levels?

I mean if I have one risk assess with project level risk scoring, how the same risk will be assess with portfolio risk scoring ?

If I have VH with 100 $ at cost project level, PRA will assess VH with 1 mil $ at portfolio level. This situation is unacceptable.

Please advice !

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts