Revised and Recovery Plan

Dear Planners,

Can any one tell me accurately what is the difference between "Revised Plan" and "Recovery Plan", and in which cases they are used?

Best,

Moutaz

A
Ahmed KHR 👤 Member for 15 years 6 months

We revise a programme in case of EOT, scope change (addition or deletion), Quantities changes

Recovery plan is the way to absorbe the delay and turn back to the original project finish date.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Moutaz

You prepare a recovery plan to try to reduce a delay situation.

You revise a plan if there is a different way of doing things.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts