Progress update of out of sequence activities

S
Sunil Babu 👤 Member for 15 years 6 months

Dear All,

What will be the effect of  updating an out of sequnce activity in a Baseline programme (Cost loaded) in a Villa Project.

Planned dates of that activity falls in the month of May, but actvity completed in the schedule period. (Schedule % is 0, Activity % is 100).

How will it affect the Performance %  ?. Settings for EV calculations are as follows.

1. Performance % equal to Activity %

2. ETC is equal to remaining cost.

3. Budgeted values with current dates.

4. Progress override

Best Regards,

Sunil.