P6 RESOURCE PROFILE

Dear Planners,

I would like to brought this to the group to get information how my resource graph shows like a step of a stair as per attachment. May someone could make me understand/explain how to make this profile smooth. The Time scale is in weekly progress Plan. But if it is in monthly (timescale) it shows good.

 

Thank you,

 

Cecil

p6_resource_profile.jpg

R
Raymund de Laza 👤 Member for 16 years 6 months

Cecil,

In User Preferences.. Resource Analysis.. Set the interval to days...

 

 

Regards,

Forum Sponsor