I need the sequence of work and relationship for the following Electrical activities
Embedded Conduiting in the Floor SlabConduiting in BlockworksInstallation of TrunkingInstall Cable TrayWiring for LightingWiring for PowerWiring for Fire AlarmWiring for Emergency Lighting SystemDressing & Termination of Fire AlarmWiring for IP CCTVDressing & Termination of Emergency LightingWiring for SMATV SystemDressing & Termination of SMATVWiring for Structured CablingWirng for BMSDressing & Termination of Structured CablingDressing & Termination of BMSDressing & Termination of CCTVUninteruptable Power Supply (UPS)Central Battery SystemInstallation of BMS
Thanks in advance
conduit, wire then terminations
in slab would be first
then the highest component in the ceiling
then any in-wall work
conduit, wire then terminations
in slab would be first
then the highest component in the ceiling
then any in-wall work
Hi Project
That is too much detail.
You need to split the MEP into 3 tasks - Ducting > Pipework> Containment.
These are place vertically in risers and horizontally in ceiling zones and / or floor zones.
Cables are placed in the containment after weather tight conditions.
IT cables have seperate containment and must not be placed close to HV / LV cables.
Best regards
Mike Testro