MEP Sequence

I need the sequence of work and relationship for the following Electrical activities

Embedded Conduiting in the Floor SlabConduiting in BlockworksInstallation of TrunkingInstall Cable TrayWiring for LightingWiring for PowerWiring for Fire AlarmWiring for Emergency Lighting SystemDressing & Termination of Fire AlarmWiring for IP CCTVDressing & Termination of Emergency LightingWiring for SMATV SystemDressing & Termination of SMATVWiring for Structured CablingWirng for BMSDressing & Termination of Structured CablingDressing & Termination of BMSDressing & Termination of CCTVUninteruptable Power Supply (UPS)Central Battery SystemInstallation of BMS

Thanks in advance

Z
Zoltan Palffy 👤 Member for 16 years 10 months

conduit, wire then terminations

in slab would be first

then the highest component in the ceiling 

then any in-wall work 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

conduit, wire then terminations

in slab would be first

then the highest component in the ceiling 

then any in-wall work 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Project

That is too much detail.

You need to split the MEP into 3 tasks - Ducting > Pipework> Containment.

These are place vertically in risers and horizontally in ceiling zones and / or floor zones.

Cables are placed in the containment after weather tight conditions.

IT cables have seperate containment and must not be placed close to HV / LV cables.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts