Hello every one,
I have cost loaded baseline plan and also have an updated baseline plan.
I have noticed that if a task is 100% completed its
AT COMPLETION TOTAL COST value
becomes "0"
where as my client is asking me that value of
Budgeted Total Cost should be equal to At completion Total Cost.
Can any one please let me know where I am lacking and what will be the solution.
Thanks for your time.
Regards