Activity % Complete

Hi Members,

Can anybody help me with updating activity % complete from importing excel file. I am currently facing issues in this. I can and have been able to export my p6 file to excel, update and re-import and its all working fine for BudgetedTotal Cost, Budgeted Unit, Duration and so on. But for Activity % Complete, it is not working?

 

Pls Help

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Yakubu

There are two conditions to maintain this item manually:

1. The activity must be started, as Jerome wrote

2. Percent complete type must be physical. For the two other types (duration, units) it is always calculated by P6.

Regards

Dieter

J
Jerome Odeh 👤 Member for 22 years 4 months

Hi Yakubu,

You also need to update Actual Start Date for the updated Activity % Complete to be reflected.

 

=jerome

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts