Hi Members,
Can anybody help me with updating activity % complete from importing excel file. I am currently facing issues in this. I can and have been able to export my p6 file to excel, update and re-import and its all working fine for BudgetedTotal Cost, Budgeted Unit, Duration and so on. But for Activity % Complete, it is not working?
Pls Help
Hi Yakubu
There are two conditions to maintain this item manually:
1. The activity must be started, as Jerome wrote
2. Percent complete type must be physical. For the two other types (duration, units) it is always calculated by P6.
Regards
Dieter
Hi Yakubu,
You also need to update Actual Start Date for the updated Activity % Complete to be reflected.
=jerome