i prepared plan. later on i added few WBS along with activities. when i updated plan i am facing following problem.
The activities are showing performance and schedule percentages where as newly added WBS are not showing percentages.
Kindly guide me to rectify this error.
Your schedule needs to be cost loaded for progress to roll-up to WBS level.
Assign cost to the new activities and their WBS will display performance & schedule % completes.