Updating Multiple Resource Loaded Activities

Hello,

I am updating a project that has activities with multiple resource assigned to them.  However, when I update the activity with a new percent complete and actual hours - it does apply the same percent complete to indiviual resources and the actual units does not distribute evenly.  Rigt now I have to go into the Resource assignments tab and update indivual resources instead of activities.

 

Right now  am using Fixed Units as my duration type & units percent complete.

 

Any help would be greatly appreciated.

Kaitlin

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts