Update OPtions

hey all ,, I've start my new jop as a planner engineer, i want to konw how to set the update Options in the P6 because i think that there is a problem ,, when i update an activity that isn't finish yet, by mark it as started and insert a percentage of complete the float jumb to be very larg !!,,so i realy need to know how can i go to the options of the update and try to solve this problem ,,

 

  Thanks,,

G
Gary Whitehead 👤 Member for 17 years 2 months

Sounds more like a problem with the logic than the update options to me.

 

What successor relationhsips does the activity in question have? (finish to start, start to start, etc)

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts