Auto Actual Cost

Dear All,

If anybody can help me on the following topic as earliest, it will be very helpfull..

During my updatation of the activities, actual cost is not getting updated against the percentage completion only for some activities.  i already turned on auto compuet actuals and calculate cost from units options in resource window.  

can anyone in the forum help me to fix this issue?

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts