Implication to resources in early and late schedule

T
Tim Tam 👤 Member for 13 years 1 month

Hi,

Can I enquire if the contractor is to commit to the resources and equipment loaded in the loaded schedule ?

And are they also suppose to commit to the resources in the late schedule as well, from the late start/finish ?

The peak resource requirement is going to differ , and are there also any guideline On the appropriate % difference ?

Br

R
Ronald Winter 👤 Member for 23 years 5 months

Tim,

The answer to your question and many like it is, “What does the contract say?”  If it is not mentioned in the contract, then the contractor is not required to do it.  Good luck!