Duration difference after exporting P6 to MPP

V
Vic Noztua 👤 Member for 12 years 8 months

Hi!

Please need help.

After exporting a P6 project to MPP, several activities durations are showing incorrect durations - however you tried to correct the start and finish dates the duration stays incorrect?

 

Thank you in advance!

V
Vic Noztua 👤 Member for 12 years 8 months

Hi Mark. Many thanks for the help. I just re-create the incorrect duration activities in MPP, and yes I believe too that calendars has something more to do with these problem. Have a good day.

M
Mark Sales 👤 Member for 18 years

Hi Vic,

 

There are several things that could cause that.

Firstly, you may have working time in P6 which is non-working time in MS. Check your calendars, weekends, bank holidays etc.

Also, has this occurred on LOE of summary bars? Th eimport process could alter these.

If you have any further trouble, delete these few activities and then re-create them.

 

Regards

 

Mark

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts