Dear colleagues,
I'd exported a project from P6 R8.2 to MS Project, but the row from P6 that shows project name, total duration of project, start and projected finish date of project doesn't appears in MS Project format.
I look forward you could help me with this. Thank you.
Regards.
Missing Row when P6 Exported to MS Project
Forum Sponsor
Top Posters
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
Thank you very much. But this is what happened I did...from menu bar, I clicked TOOLS then OPTIONS then VIEW tab. Under Outline options for '(project name)' I checked the box Show project summary tasks then the uppermost row appeared.
To Options, go to the Project Options and display the Project Summary bars, or add the bar by creating a summary bar.
Regards
Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia
www.eh.com.au, www.eastwoodharris.com, www.primaskills.com.au and www.primavera.com.au
Project Control Consultants and Planning and scheduling software book and training material publishers