3 in one schedule - HOSPITAL

V
venu kauk 👤 Member for 12 years 11 months

If any one has a civil + MEP + HVAC combined schedule for a multi speciality 200 bed hospital project send me a copy



Many Thanks

 

use private message service

S
SANTOSH KUMAR PRASAD 👤 Member for 15 years 9 months

Dear

Create decipline WBS and breakdown the activities,

- Discussed with all diciplined Engineers and with project Manager

- Develop the schedule as requirements of your project.

WBS

General Requirements

Design & Engineering

 - General

 - Civil

 - Mechanical

- Electrical

 - Instrumentation

like...this

 

Thanks