Dear All,
WE know that SPI and CPI are calculated by p6 and we only need to open the columns to see the values.
I want to know, is it possible in P6 to have a month wise SPI & CPI from the start of the project to the current date. If it is possible please tell me how?
Regards,
Malik
what if you grouped by Start then make the Interval Month ?
How do I set up a schedule so that it calculates SPI correctly? What % complete types, settings, etc?