Create S curves with MS PROJECT or PRIMAVERA P6

 

The S curves, the only way to measure the physical progress of a project. 

  • Create 26 S curves (baseline early and late, physical progress) in automatic connection with a MS PROJECT or PRIMAVERA P6 schedule.
  • Spread the weights in a linear or Gaussian way over the tasks of schedule.
  • Create S curves with 3 criteria, on the basis of 5 task codes.
  • Manage a schedule up to 10,000 tasks.

  To buy the VBA EXCEL application: http://www.cubixpm-scurves.com/en/

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts