Hello friends,
I have a small problem regarding the number of duration for activities. Example: Activity 1 has the original duration as 5 days. but the dates are as follows,Start -- 20 feb 2013Finish -- 25 feb 2013 But if we count the number of days, it actually 6 days..I need finish date should be 24 feb 2013. 1st day -- 20 feb 20132nd day -- 21 feb 20133rd day -- 22 feb 20134th day -- 23 feb 20135th day -- 24 feb 2013 is it any setting problem??? please help me to sort out. Thanks,Sivaganesh
thanks everyone....
Gary,
it is correct but confusing.
Start at 8am on 20th of February and Finish at 17pm on 24th of February is also correct but not confusing.
Finishing project on Friday evening or on Monday morning is the same but those who want to use the product on Saturday may be disappointed.
Sivaganesh,
Check this in your Schedule.
20 Feb = 8:00am - 5:00pm
21 Feb = 8:00am - 5:00pm
22 Feb = 8:00am - 5:00pm
23 Feb = 8:00am - 5:00pm
24 Feb = 8:00am - 5:00pm
Day 1
20 Feb = 12:00pm -
21 Feb = - 11:59am
Day 2
21 Feb = 12:00pm -
22 Feb = - 11:59am
Day 3
22 Feb = 12:00pm -
23 Feb = - 11:59am
Day 4
23 Feb = 12:00pm -
24 Feb = - 11:59am
Day 5
24 Feb = 12:00pm -
25 Feb = - 11:59am
Sivaganesh,
If you start activity 1 at 8am on 20th Feb, and it is 5 days duration, it will finish at 8am on 25th Feb.
This is correct.