Loading of Cost in P6 by Importing Excel File

Dear Frnds,

i am trying to loading cost for the activities in P6 program by importing cost loaded in excel file but it is not getting loaded.

Could some1 please help me by listing out the sequence of operations required or what would be problem in loading cost.

 

Thanks in advance,

Rahul Jaiswal

J
Jerome Odeh 👤 Member for 22 years 4 months

Rahul,

Check that you are not trying to import a calculated field into P6.

 

J