CASHFLOW RECOVERY

D
Dura Cell 👤 Member for 15 years 6 months

Hi all!

 Need some advise on how to deal this situation.  Everytime I update the program monthly, our cashflow is below as planned.Project manager want me to recover the cashflow for us to obtain exactly the baseline end date of the project. This cashflow recovery is happened twice already, and I am very concern what would happen in the future if we will keep doing cashflow recovery. My cashflow chart has only two elements, planned amount and recovery amount. There is no actual amount. Now my question, is this kind of practice accepted in planning procedure? Any explanation to clear this subject? Hope you understand my question. Thanks PP members!  

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts