Bringing whole schedule in by a month

S
S M 👤 Member for 13 years 8 months

I have a schedule which the PM has asked for me to bring in by an entire month.

He wishes to know which items (which perhaps aren't critical now) would become critical if the whole delivery was brought in by a month.

I realise there a number of ways to do this (finish on/mandatory constraint, Filters etc.) but I was wondering what others or experienced PPs would do.

Thanks

M
Mike Testro 👤 Member for 20 years 5 months

Hi S M

Assuming that the programme has been put together properly then the correct way to bring it in by one month is to:

1. Review the logic.

2. Increase resource levels on critical items - if workfront density allows.

3. Work overtime / weekends on critical items.

4. Check Non-Work days on the calendars.

Never do it by use of artificial constraints.

The first assumption will be your main problem because if the programme is already riddled with fundamental errors you will never get a realistic answer.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts