Primavera Project Duration

Hi,

Would like to ask some help with regards to the image below. Have asked a subcontractor to provide an EOT and to use the latest update of the schedule without the baseline. I've noticed that in Primavera 8, the duration of the civil works doesn't seem to tally. Looking at the program that it still uses the original plan dates, allthough there are no baseline. This is only showing to activity with actual dates, is this an anomaly of Pv8 if it's then what are the remedial of this?

Need advice and ragards.

 

p3_jpga.jpg

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts