METHOD OF RESOURCING THE SCHEDULE IN P6

D
Dura Cell 👤 Member for 15 years 6 months

Dear All,

 I just wanna ask some help regarding the METHOD OF RESOURCING THE SCHEDULE. I already populated my 510 activities with all the resources required. Now my problem is when I calculated average per month the result is 1800. I am expecting a value ranging from 400-600 on the peak months.

 If you could give some advise on how to do this. Any help is very much appreciated.

 Thanks pp members

A
Andrew Tan 👤 Member for 21 years 8 months

Hi,

Much like Raymund.

1. Make sure you set interval calculation first to Month for your case. Perhaps this will take care already.

2. In the top pane, open the P6 table that shows resources distrbution per activity.

3. In the bottom pane, shows the graph options that shows resource histogram.

4. With these two pane, go to the activity (top pane) and see the month (bottom pane) with most resource and try to adjust the date or duration in order to level. Repeat.

R
Raymund de Laza 👤 Member for 16 years 6 months

Dura,

In User preferences.. Resource analysis.. set the interval to the desired time interval.

Also, in the Spreadsheet or graph options in the resource distribution pane, click the calculate average and the the based on hrs per time period.

Hope this will help.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts