Project tracking - Updating in MPP 2003

Hi,

I need help for project update,

I have a master schedule of 1350 activities with only task's (no resources and cost) I have saved baseline and inserted column

of Baseline duration and baseline start and finish, and also inserted actual duration and actual start and finish columns and

%age complete for tracking, I m updating actual data like %age complete inserting in activities and start date and finish date as per actual progress. I have also inserted column of start and finish for future progress (to see as planned start and finish) also overall project.

My question is that I have inserted progress in actuals column but in start and finish column (for Future start and finish according ot actual) is same also those activities which dates have been passed and start and finish columns like freezed.

 

thanks and regards,

Mkumar Khatri

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts