Can we link the start and finish dates of different steps in an activity to the start and finish dates of the activity itself.
Thanks for your reply to this.
Blessan
Hi,
Can we link the start and finish dates of different steps in an activity to the start and finish dates of the activity itself.
Thanks for your reply to this.
Blessan
Nope, there is no such linking of steps in the same activity.