Problems Importing between 8.0 and 7.1

A
Aidan Kelly 👤 Member for 15 years 1 month

Hi All

I just arrived on a project where they are using P6 8.0.

As I only have 7.1 on my machine the planner exported a xer file in 7.1 so i could view the schedule.

When i do a resource report there are some discrepancies.

If i run  RA-01  Resource Assignments report in certain cells the figures will be staggered. e.g the description will be in the planned units cell the planned units in the planned start cell etc.

Any ideas why this may be happening?

Thanks in advance.

Aidan

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts