Hi All,
I am having some issues with budgeted qtys/actual qtys/ remaining qtys.
My example is a simple one, I have an activity - Open Drain Lining. I have added a material resource and assigned a total qty of 710sqm. The task itself has now started and is now expected to take 2x a long. This is were my problem kicks in, my budgeted qty now increases and the actual/remainig units are out of whack. I have tried several activity types to no avail. I would love the budgeted qty to remain the same and the actual/remaining units total the budgeted qty no matter how long or short the activity duration is.
What I would like to see is even if the lining took 2 years it is still 710 and the remaining/actual is a product of the 710 based on % duraiton complete. This is playing having with my actuals complete and hence throwing out my % complete, overall progress.
Thanks heaps, just when you think you have P6 nailed you get more issues.
Thanks Chris, works great. Im liking this planning planet, its an uphill battle learning yourself
Thanks Chris, works great. Im liking this planning planet, its an uphill battle learning yourself