Schedule Logs

Dear fellow planners,

I would like to get your background on how you are using "Schedule logs" created after calculation.

I mean, there is a lot of interesting information in it like errors or warnings (Activities w/o pred, w/o succ, with invalid relationship,...).

Firstly, this is a good report to clean some hidden mistakes but:

- Do you use it for other purpose (like claim, internal analyse,...) ?

- Do you compare rate of relationship Qty to Activities ? What is telling you that a schedule is not linked or too much ?

- ...

Well, if anyone has good idea on how to fully use this report, I will appreciate to get your feedback,

regards