Performance % Complete

P
planner bim 👤 Member for 14 years 4 months

Dear Seniors,

 

Can you please advise how Performance % complete works in P6? Thanks

 

Regards,

BIM

A
Anning Sofi 👤 Member for 14 years 4 months

Performance complete is a function of actual cost in relation to cost at completion in a cost loaded programme, generally used for EV analysis.  It can be on activity level or at summary level.The performance complete value is usually the activity %complete value. (Not the unit%, duration% or physical %).Also, the values in the performance complete are stored whenever you execute the store project performance function.

J
James Buxey 👤 Member for 21 years 8 months

Hi

 

Performance % complete is a 'roll up' of all EV earned through Physical % complete

Ie if you have a number of tasks that collectively add up to a EV £100 and the total budget is £1000 the Performance % complete is 10%

 

Hope this helps

 

Regards

 

James

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts