Progress on WBS and Project Level

P
planner bim 👤 Member for 14 years 4 months

Dear Seniors,

 

I am new in Planning. Can you please guide me.

What is the best way to measure progress at WBS level and Job level on a project having 500+ activities and 26 WBS, without cost/ resource loading. I selected the option "Performace % Complete" also. After inputting the % Completion in Activity % Completion, I am not getting the % at WBS and Project level.

Please guide me on this.

 

Thanks,

BIM

V
Vijay Anbumani 👤 Member for 14 years 5 months

Hi Bim,

        I am not much more experienced but i feel i can help you on this, no problem cost or resource not needed but are u using the planning tool of Primavera 6 or MS project. the % Completion u selected is rite but you have to update the schedule. check the progress update and select the regarding month to be update, so u will get it.

where are you working Bim.

Yur, & best wishes.

J. Vijay

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts