Dear Seniors,
I am new in Planning. Can you please guide me.
What is the best way to measure progress at WBS level and Job level on a project having 500+ activities and 26 WBS, without cost/ resource loading. I selected the option "Performace % Complete" also. After inputting the % Completion in Activity % Completion, I am not getting the % at WBS and Project level.
Please guide me on this.
Thanks,
BIM
I suggest you dont use Perfomance % if your schedule is not cost loaded.
Hi Bim,
I am not much more experienced but i feel i can help you on this, no problem cost or resource not needed but are u using the planning tool of Primavera 6 or MS project. the % Completion u selected is rite but you have to update the schedule. check the progress update and select the regarding month to be update, so u will get it.
where are you working Bim.
Yur, & best wishes.
J. Vijay