Recurring Task like meeting or Testing

Can someone tell me what is the best way of creating repeat activities in P6 V7, i have 2500 columns that i am constructing and i need some form of testion on all of them, i dont wish to write 5 activities of testing per column repeated 2500 times, is there a way to do this like in MSP you have recurring task?