I'm semi-new to P6.
I'm trying to hold a date in my schedule. In the bottom activity box I have the dates selected that I want to hold, but in the schedule the * does not appear. When I update the schedule, it changes all 100% completed dates to the data date. If I change the data date, it changes all 100% done activities to that data date.
Any input would be apreciated.
Dave