Project tracking problem

Hello everyone

I am using a schedule of 5000 activities ...there are lot of packages  in the schedule & the activity duration is also vey less like 2 hours , 6 hours , and as a whole package the duration become 300 hours ...but i want to show all 5000 activities in schedule, Now the probelm is How to track the activities of small duration ...I mean 2hours , 4 hours etc...Its difficult to Track my schedule ...Any Sugessitions...

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts