Inporting XER to Primavera Risk Analysis

S
SM PUM 👤 Member for 14 years 6 months

Hello All Planners,

I have Imported an XER file to Primavera Risk analysis but it is not showing WBS Bands.Only activities are listed.Any Suggestion?

 

Regards

S
srinivas doguparthy 👤 Member for 14 years 5 months

i am having doubt in calenders

when i am giving daates to activities from 24-12-2011 to 08-01-2011

the original duration should be 16 days but it is showing 30 days

 

how to resolve this problem

 

when i am exporting the project and saving

again when i am importing this project in primavera project details are coming but i am not getting OBS and EPS

how to get this

 

how can i change the order of activities in p6.7

a1000

a1500

a1250

a1450

i should make it in correct order how to do

 

 

please help me in these issues it will be very much helpfull to me pls pls pls pls

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts