Hi,
I have activity calender equal to 10hr/D, and the default hours/Days is 8h/days.I have changed 8hr/Day into 10Hr/Day. My Question is,
Is there need to change the hrs/week ,hrs/month and hrs/year values or Primavera itself will take these values from the new hrs/day value?
Regards,
How to change the preference in primavera
When i am making the schedule through primavera than preference setting is set for earlier date finish the activity than it going upper otherwise activity going lower
How to change the preference in primavera
Just remember that not all P6 versions are equal and that in P6v7 the following applies.
Good Luck
AB,
It is fairly simple to reason out your question if you understand the mechanics involved. If you have P6 set to display days, then it will assume that when you enter a number without a qualifying “d” or “h” after it, that you meant to enter the number as ‘days’. P6 only stores all durations in hourly figures.
P6 will take your ‘days’ entry and convert it to ‘hours’ using the conversion factor you have set and store that number. If your number entered was “4” and the conversion factor was ‘8 hours per day’, then P6 stores 4 x 8 = 32.0 in the database.
Later, you might change the conversion factor to ’10 hours per day.’ When you ask P6 to display that previously-stored number, P6 will retrieve the 32.0 and divide by the conversion factor (now ’10 hours per day’) and will display, 32 / 10 = 3.2. If you set the display to only show round numbers, then P6 will display “3”. Your “4” has now become a “3”. I hope that this answers your question. Good luck!
is there need to change the hrs/week ,hrs/month and hrs/yearvalues or Primavera itself will take these values from the new hrs/day value?
My guess, as I do not use P6, is that the new default will take over only on new data entry, it shall not disturb data previously entered, so it can make sense to change it as needed. If you have the newer version 7 it will work using the averages computed from the activity calendar except on the summary bars when activities use different calendars it will use the default. Note this shall be verified against the different versions.
For example if calendar 1 is based on the following work week; Sun = 8 hrs./day, Mon = 8 hrs/day, Tue = 8 hrs/day, Wed = 8 hrs/day, Thurs = 8 hrs/day, Fry = 8 hrs/day, Sat = 8 hrs/day
= 56 hours per week = 7 work days [days with assigned hours no matter if 1 or 2 hours] = 56/7 = 8 hours/day
In this case when you enter 1 day the software will assign 8 hours.
If calendar 1 is based on the following work week; Sun = 0 hrs./day, Mon = 8 hrs/day, Tue = 8 hrs/day, Wed = 8 hrs/day, Thurs = 8 hrs/day, Fry = 8 hrs/day, Sat = 0 hrs/day
= 40 hours per week = 5 work days [days with assigned hours no matter if 1 or 2 hours] = 40/5 = 8 hours/day
In this case when you enter 1 day the software will still assign 8 hours.
Not the same work days per week but same hours/day.
If calendar 1 is based on the following work week; Sun = 4 hrs./day, Mon = 8 hrs/day, Tue = 8 hrs/day, Wed = 8 hrs/day, Thurs = 8 hrs/day, Fry = 8 hrs/day, Sat = 4 hrs/day
= 48 hours per week = 7 work days [days with assigned hours no matter if 1 or 2 hours] = 48/7 = 6.857 hours/day
In this case when you enter 1 day the software will assign 6.857 hours
The issues you are having are not exclusive of any software, almost all must change from days to hours using some factor, a factor that will vary in some as you apply days amount to your calendars, others will use a single factor. The multiple factor makes it easy for weeks where all days have same amount of work hours but when you have a week with different work hours per day the days assignment will still be prone to confusion.
Secondly if you see the default working hours for 8hr/Day,then how is Hourz/Month and hours/year is calculated by Primavera,because if you see in Time period option in user preferences there are
8hr/Day ,40 hr/week ,172Hr/Month and 2000Hr/Year (Default).
But if you calculate using 5 d/w & 8h/d calender (Default Calender) it becomes
40hr/week & 40*4 = 160 hr/month & 160*12=1920 Hr/year. why is this difference?
Can you please explain me these calculations a bit.i am Confused :(
Regards,
Hi Rafael,
Thanks for Answering.Thanks for the link also.my Question was,
is there need to change the hrs/week ,hrs/month and hrs/year values or Primavera itself will take these values from the new hrs/day value?
Regards,
The following link can be of interest to you.
http://thesimplexgroup.wordpress.com/2011/03/10/converting-from-work-hours-to-work-days-weeks-etc-in-p6/
In P6, do you get confused when the Admin, Preferences are set to have 1 day equal 8 hours, but you’re working with 10-hour days instead; so, when you set your user preferences to show days, it’s showing 1.25 days instead of 1? Well, Primavera P6 Rel 7 has a fix for that! You can now choose to convert from hours to days, weeks, etc., based on the calendar assigned to the activity instead of the Admin, Preferences.
I use other software that as a default uses activity calendar, still you got to be aware that when the weeks have different hours per day it can still be confusing.
One way to avoid the issue is work in hours durations only, avoiding the average hours/day factor.